Environmental Compliance

Not Started
In Progress
Passed
PassedPlus
Failed

Permits, Licenses, Statutory

Status: In Progress

BASIS OF ASSESSMENT: Work In Progress on the basis of a completion of an SLF Preliminary Assessment Visit (PAV), conducted on 11 September 2025..

EVIDENCE: Onsite PAV conducted.

NEXT STEPS: Work to continue in line with the PAV report to prepare for formal audit.

EMS

Status: Not Started

Environmental Health & Safety

Status: In Progress

BASIS OF ASSESSMENT: Work In Progress on the basis of a completion of an SLF Preliminary Assessment Visit (PAV), conducted on 11 September 2025..

EVIDENCE: Onsite PAV conducted.

NEXT STEPS: Work to continue in line with the PAV report to prepare for formal audit.

Environmental Footprint

Status: Not Started

Land use

Status: In Progress

BASIS OF ASSESSMENT: Work In Progress on the basis of a completion of an SLF Preliminary Assessment Visit (PAV), conducted on 11 September 2025..

EVIDENCE: Onsite PAV conducted.

NEXT STEPS: Work to continue in line with the PAV report to prepare for formal audit.

Energy Consumption

Energy Consumption kWh/m2 of leather

100 kWh/m2
0 kWh/m2
Average from Tanned to Finished kWh/m2
Company’s actual consumption kWh/m2


PT Nasional Djawa Kulit Annual Energy Consumption: kWh

Energy Consumption

Status: In Progress

BASIS OF ASSESSMENT: Work In Progress on the basis of a completion of an SLF Preliminary Assessment Visit (PAV), conducted on 11 September 2025..

EVIDENCE: Onsite PAV conducted.

NEXT STEPS: Work to continue in line with the PAV report to prepare for formal audit.

Water Use

Water Use L/m2 of leather

100 L/m2
0 L/m2
Average from Tanned to Finished L/m2
Company’s actual consumption L/m2


PT Nasional Djawa Kulit Annual Water Use: ML

Water Use

Status: In Progress

BASIS OF ASSESSMENT: Work In Progress on the basis of a completion of an SLF Preliminary Assessment Visit (PAV), conducted on 11 September 2025..

EVIDENCE: Onsite PAV conducted.

NEXT STEPS: Work to continue in line with the PAV report to prepare for formal audit.

Raw Materials & Chemicals

Status: In Progress

BASIS OF ASSESSMENT: Work In Progress on the basis of a completion of an SLF Preliminary Assessment Visit (PAV), conducted on 11 September 2025..

EVIDENCE: Onsite PAV conducted.

NEXT STEPS: Work to continue in line with the PAV report to prepare for formal audit.

Machinery & Equipment

Status: Not Started

Air Emissions

Discharge ParamenterRegulatory Limit mg/lActual DischargeCategory Band
Boilers (NOx)
Boilers (SO2)
Spray Machines - Particulates
Spray Machines - Nitrogen Oxide (NOx)
Spray Machines - Carbon Monoxide (CO)
Toggling - Nitrogen Oxide (NOx)
Toggling – Carbon Monoxide (CO)

Air Emissions

Status: Not Started

Effluent Treatment

Discharge ParameterRegulatory Limit mg/lActual Discharge mg/lCategory Band
Chemical Oxygen Demand (COD)
Biological Oxygen Demand (BOD)
Total Kjeldahl Nitrogen
Total Nitrogen
Ammonia Nitrogen
Suspended Solids
Oil & Grease
Chromium VI
Total Chromium
Dissolved Oxygen
Phoshorous
Phenol
pH Range
Sulphides
Chlorides
Synthetic Detergent Limit
Copper
Cyanide
Lead
Mercury
Nickel
Cadmium
Zinc
Sulphates
Total Dissolved Solids

Effluent Treatment

Status: In Progress

BASIS OF ASSESSMENT: Work In Progress on the basis of a completion of an SLF Preliminary Assessment Visit (PAV), conducted on 11 September 2025..

EVIDENCE: Onsite PAV conducted.

NEXT STEPS: Work to continue in line with the PAV report to prepare for formal audit.

Soil Contamination

Status: Not Started

Solid Waste

Status: In Progress

BASIS OF ASSESSMENT: Work In Progress on the basis of a completion of an SLF Preliminary Assessment Visit (PAV), conducted on 11 September 2025..

EVIDENCE: Onsite PAV conducted.

NEXT STEPS: Work to continue in line with the PAV report to prepare for formal audit.

You are not logged in

To see the detail behind the dashboard you will need to log in. If you need a password reminder or if you would like details of how to become a partner of the Foundation please contact us and we will be happy to help.